Evaluation of two M & E variation final accounts, each in excess of £2m
in preparation for adjudication referrals; acting for a major UK contractor.
Complete re-measurement of £3m traditional school project
including evaluation of all variations; acting for London local authority.
Ascertainment of costs in respect of prolongation, overheads,
finance charges and interest on a variety of loss & expense claims, mostly
being referred to adjudication or arbitration proceedings.
Contract and cost administration of all disciplines comprising
£200m process engineering expansion project including administration of
follow on term contracts; acting as the client's representative.